New Jersey American Water will be performing multiple water main replacement projects in Cherry Hill for the next several months. The company has begun approximately $1.75 million in projects to install more than 9,800 feet of main throughout the municipality.
The new water mains, which are replacing aging pipes, will be constructed along the following streets:
- Blue Jay Lane, between Liberty Bell Drive to Peacock Drive
- Burning Tree Road, between Shelly Lane and Covered Bridge Road
- Saint Johns Drive, between Shelly Lane and Burning Tree Lane
- King George Road, between East Chapel Avenue and Cornwall Road
- Kingsport Road, from King George Road to the road’s end
- Preston Road, between Lee Ann Road and Cornwall Road
- Lantern Lane, between Jade Lane and Ivy Lane
With the installation of the new water main, New Jersey American Water customers should experience increased water flows, more reliable water service and fire protection.
Final street restoration will be completed in summer 2016.