Areas around Burlington Township High School will see repavement to its streets starting mid-July.
With summer break kicking into effect, the Burlington Township High School lots will see some roads repaved in the coming weeks.
Drivers are expected to use caution when traveling around these areas, and also plan accordingly with traffic and scheduling. Here is a tentative list of dates and areas for the repavement schedule.
Also, due to repaving, Central Registration will move to the HS Main Building, D-Wing for the summer. The tentative dates for the relocation are July 24 to August 10.
- July 19 to July 27: Jacksonville Rd. entrance will be closed, but the BOE parking lot open and accessible only through Fountain Avenue entrance.
- July 28 to August 4: Jacksonville Rd. entrance will be open, but the BOE parking lot will be closed for paving. Visitors to Hopkins must park in the small lot by the Hopkins Main office (Loop)
- August 5 to August 11: Board of Education parking lot will reopen but you must enter through the Jacksonville Rd. entrance, due to the closure of the D-Wing fire lane (next to the softball field).
- August 14 to August 15: Striping (may take place in late afternoon) Please check for updates for the impact from the striping on various lots.